Comparative Analysis of Planned and Actual Progress in Road Projects Using Schedule Performance Index

Authors

  • Adi Iswanto Universitas 17 Agustus 1945 Samarinda image/svg+xml Author
  • Tukimun Universitas 17 Agustus 1945 Samarinda image/svg+xml Author
  • Benny Mochtar Effendi Arifin Universitas 17 Agustus 1945 Samarinda image/svg+xml Author

Keywords:

Project Management, Schedule Performance Index, Time Evaluation

Abstract

This study aims to evaluate the time performance of the Teratak – Muara Kaman Ilir Road Reconstruction Project by comparing planned and actual cumulative progress using the Schedule Performance Index (SPI). The research employs a descriptive quantitative method with a single case study approach on a district-funded road project in Kutai Kartanegara Regency, Indonesia. Weekly progress data were analyzed over a 16-week execution period. Results show the lowest SPI occurred in week 4 at 0.170, while the highest SPI was recorded in week 7 at 3.663. The SPI trend graph indicates a fluctuating pattern, with delays in early weeks, significant acceleration in the middle phase, and stabilization toward project completion. The SPI returned to 1.000 in week 16, indicating on-time project completion. These findings highlight that schedule recovery strategies effectively brought project execution back on track. However, the sharp fluctuation in SPI also suggests the need for more consistent and sustainable schedule control. The study confirms that SPI is a useful tool for time monitoring in construction projects, though it should be integrated with qualitative analysis to better understand the underlying causes of performance deviations.

References

Azeem, S. A. A., Hosny, H. E., & H.Ibrahim, A. (2014). Forecasting Project Schedule Performance Using Probabilistic and Deterministic Models. HBRC Journal, 10(1), 35–42. https://doi.org/10.1016/j.hbrcj.2013.09.002

Elsaid, M., NassaR, K., Alqahtani, F. K., & Abotaleb, I. (2025). Comparative Analysis of Earned Value Management Techniques in Construction Projects. Scientific Reports, 15(23606). https://doi.org/10.1038/s41598-025-05834-z

He, C., Liu, M., Alves, T. da C. L., Scala, N. M., & Hsiang, S. M. (2022). Prioritizing Collaborative Scheduling Practices Based on Their Impact on Project Performance. Taylor & Francis: Construction Management and Economics, 40(7–8), 618–637. https://doi.org/10.1080/01446193.2022.2048042

Janshar, A., Sutikno, & Sutantio, A. (2025). Optimasi Peran System Application and Product dalam Manajemen Pengendalian Biaya pada Proyek Konstruksi Design and Build. Jurnal Locus: Penelitian Dan Pengabdian, 4(9). https://doi.org/10.58344/locus.v4i9.4799

Kumar, M., & Kumari, S. (2025). Causes of Delay in Road Construction Projects: A Systematic Review. Journal of Financial Management of Property and Construction, 30(2), 256–294. https://doi.org/10.1108/JFMPC-01-2023-0004

Le-Hoai, L., Lee, Y. D., & Nguyen, A. T. (2013). Estimating Time Performance for Building Construction Projects in Vietnam. KSCE Journal of Civil Engineering, 17(1), 1–8. https://doi.org/10.1007/s12205-013-0862-3

Lennie, J., & Tacchi, J. (2013). Evaluating Communication for Development: A Framework for Social Change. Routledge.

Malingkas, G. Y. (2025). Time and Cost Management Analysis Using the Schedule Performance Index (SPI) and Cost Performance Index (CPI) Methods in the Community Health Center Construction Project in Kakaskasen Village, Tomohon City. Journal of Social Research, 4(10). https://doi.org/10.55324/josr.v4i10.2734

Moslehabadi, A. F. (2020). Homogenizing Schedule Performance Index (SPI) in Construction Projects. International Journal of Industrial Engineering and Operational Research, 2(1), 42–50. https://doi.org/10.22034/ijieor.v2i1.20

Muharremi, U. (2025). Applying Earned Value Management for Enhanced Cost and Schedule Monitoring in Public Procurement [Politecnico di Torino]. https://webthesis.biblio.polito.it/35671/

Rahmah, N. P. N. (2025). Analisis Faktor Keterlambatan Pelaksanaan Proyek Peningkatan Jalan Lingkungan Desa Busui Kecamatan Batu Sopang [Universitas Islam Indonesia]. dspace.uii.ac.id/123456789/55264

Sackey, S., & Kim, B.-S. (2019). Schedule Risk Analysis using a Proposed Modified Variance and Mean of the Original Program Evaluation and Review Technique Model. KSCE Journal of Civil Engineering, 23(4), 1484–1492. https://doi.org/10.1007/s12205-019-1826-z

Sugiyono. (2019). Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Alphabet.

Tzonevska, D. (2023). The Economic Factor as a Key in Planning Activities of the National Road Network. IOP Conference Series: Materials Science and Engineering, 1297(012017). https://doi.org/10.1088/1757-899X/1297/1/012017